A 54-inch and a 24-inch corrugated metal pipe (CMP) under Heritage Way have been evaluated for replacement. They will be replaced with 54-inch and 24-inch reinforced concrete pipes (RCP).
Project complete December 2023
09/28/2023: NTP Issued to Blount Construction Company, Inc
10/17/2023: Reinforced Concrete Pipe Delivered
11/07/2023: RCP installation complete
11/13/2023: Concrete work complete
11/14/2023: Asphalt paving complete
11/16/2023: Final Stabilization complete
11/20/2023: Substantial Completion
12/12/2023: Final Completion & Acceptance