Antioch & Goza Roads Intersection Status: Completed Last Updated: November 20, 2019 Project Completed:

Budgeted & Pending
In Design
Under Construction
Completed
  • antiochgoza_existing_conditions.png
Click Here for Project Updates
The most recent phase of this intersection project was to convert the intersection from a two-way stop control to an all-way stop control. The intersection was realigned in 2011 to eliminate an offset between Goza Road and add turn lanes to each of the four approaches. Following conversion to the all-way stop, the intersection was resurfaced and given new striping as part of an Antioch Road resurfacing project. All work is complete.
Latest Update:

Project complete. (Last Update: 11/20/2019)

  • Approved Budget: $1,070,000
  • Revised Budget: $1,108,750*
  • Category: Intersection Improvements
  • Expended to Date: $143,134
  • Designer: Heath & Lineback Engineers, Inc.