This is an existing 4-way stop intersection that experiences heavy delays in the morning and afternoon hours. It also has multi-use paths along Redwine Road. The intent is to improve operating conditions during AM and PM peak hours and improve the ability of pedestrians, bicyclists, and golf carts to safely cross the roads.
Final plans have been approved. This project is starting the utility relocation phase.
05/19/2023 - Utility Relocation: Relocation efforts will continue once easements are secured
08/22/2023 - Utility Relocation: Further relocations pending
10/26/2023 - Construction: First phase of detour
11/27/2023 - Construction: Second phase of detour
12/22/2023 - Construction: Road opened
4/29/2024 - Construction: Cart path paving completed