110 Mark Lane Status: Design Last Updated: May 11, 2022 Anticipated Start of Construction: 2022

Budgeted & Pending
In Design
Under Construction
Completed
  • picture097.jpg
  • picture098.jpg
  • picture099.jpg
Click Here for Project Updates

A 60” corrugated metal pipe (CMP) under Mark Lane has been evaluated for replacement. The current pipe is out of round and displays signs of corrosion, joint separation, failure under road, and damage at inlet near the roadway.


Latest Update:

All survey work has been completed, final design has been approved, and the project is currently in the Right-of-Way acquisition phase. 

  • Approved Budget: $249,037
  • Category: Category II, Tier II
  • Expended to Date: $51,607
  • Designer: Pond