CalendarQuick LinksSearch

SPLOST Home Interactive Map Voter Approved SPLOST Manual Active Detour Map

Back to Stormwater Projects

130 Morning Dove Drive Status: Completed Last Updated: September 02, 2020 Project Completed:

Budgeted & Pending
In Design
Under Construction
Completed
  • morning-dove-drive-1.jpg
  • morning-dove-drive-2.jpg
  • morning-dove-drive-3.jpg
  • morning-dove-drive-4.jpg
  • morning-dove-drive-5.jpg
  • morning-dove-drive-6.jpg
Click Here for Project Updates

This is a culvert replacement project under a road that provides exclusive access to several homes in the Quail Hollow Subdivision.  Therefore, at least one lane of traffic remains open at all time. *Budget changes reflect action by the Board of Commissioners.


Latest Update:

Construction activities are complete, this project was completed in March 2020.

Timeline: 

  • 1/15/2019 ROW acquired
  • 5/06/2019 NTP issued to contractor
  • 10/14/2019 Construction began
  • 10/31/2019 Pre-cast culvert delivery
  • 11/01/2019 Utility relocations complete
  • 12/16/2019 Pre-cast retaining wall delivery
  • 1/27/2020 Culvert construction complete
  • 2/05/2020 Curb & Gutter construction complete
  • 2/26/2020 Milling of roadway complete
  • 3/09/2020 Paving complete
  • 3/23/2020  Substantial completion

  • Approved Budget: $244,389
  • Revised Budget: $492,389*
  • Category: Category II, Tier I
  • Expended to Date: $504,543
  • Designer: Tetra Tech
  • Contractor: Piedmont Paving, Inc.
Copyright © 2015 Fayette County Administration. All rights reserved.