Construction involved the replacement of an undersized 54" metal pipe with a 60" concrete pipe and headwalls. This project was in response to the December 2015 Flood Event that resulted in shoulder and pipe failure. *Budget changes reflect action by the Board of Commissioners.
Approved Budget: $44,523
Revised Budget: $44,763*
Category: Category I
Expended to Date: $44,763
Designer: Fayette County Environmental Management Department