155 Westbridge Circle Status: Completed Last Updated: July 26, 2019 Project Completed: January 14, 2016

Budgeted & Pending
In Design
Under Construction
Completed
  • 155_westbridge_circle.jpg
Click Here for Project Updates
Construction involved the replacement of failed double 36" metal pipes with a double 36" concrete pipes and headwalls. This project was in response to the December 2015 Flood Events that resulted in both pipes failing and causing immanent road failure. *Budget changes reflect action by the Board of Commissioners.
  • Approved Budget: $68,419
  • Revised Budget: $69,830*
  • Category: Category I
  • Expended to Date: $69,830
  • Designer: Fayette County Environmental Management Department
  • Contractor: Brent Scarbrough & Company