A 48” corrugated metal pipe (CMP) under Silver Leaf Drive has been evaluated for replacement. The pipe is currently failing.
Latest Update:
This project is complete.
Timeline
- 04/21/2021 - Invitation to Bid
- 05/12/2021 - Bid Opening
- 05/27/2021 - Board Approval
- 05/28/2021 - Notice of Award
- 06/11/2021 - Notice to Proceed
- 06/24/2021 - Pre-Construction Meeting
- 10/12/2021 - Waterline & Hydrant relocation complete
- 10/20/2021 - Road Closed / Detour
- 01/13/2022 - Culvert construction complete
- 02/09/2022 - Substantial Completion
- 04/27/2022 - Final Completion