223 Cedar Trail Status: Design Last Updated: October 21, 2019 Anticipated Start of Construction: TBD

Budgeted & Pending
In Design
Under Construction
Completed
  • picture097.jpg
  • picture098.jpg
  • picture099.jpg
Click Here for Project Updates
A 48” metal pipe under Cedar Trail needs to be evaluated for possible replacement. Current pipe has scoured and undercut at upstream side. Pipe is out of round, has corrosion, and no headwalls.
Latest Update:

Preliminary survey work has been completed. 65% design submittal was received on 8/20/2019 and is currently in review with County Staff.

  • Approved Budget: $58,206
  • Category: Category II, Tier II
  • Expended to Date: $36,197
  • Designer: Pond