285 Merrydale Drive Status: Completed Last Updated: September 15, 2021 Project Completed: September 15, 2021

Budgeted & Pending
In Design
Under Construction
Completed
  • merrydale-100.jpg

Construction involved the replacement of a failing 48 inch corrugated metal pipe with reinforced concrete pipe.

  • Approved Budget: $9,631
  • Category: Category III
  • Expended to Date: $31,504
  • Designer: Fayette County Environmental Management
  • Contractor: Fayette County Road Dept