CalendarQuick LinksSearch

SPLOST Home Interactive Map Voter Approved SPLOST Manual Active Detour Map

Back to Stormwater Projects

547 Kenwood Road Status: Completed Last Updated: August 26, 2021 Project Completed:

Budgeted & Pending
In Design
Under Construction
Completed
  • kenwood-087.jpg
  • kenwood-088.jpg
  • kenwood-089.jpg
  • kenwood-090.jpg
  • kenwood-091.jpg
  • kenwood-092.jpg
  • kenwood-093.jpg
  • kenwood-094.jpg
  • kenwood-095.jpg
  • kenwood-096.jpg
  • kenwood-097.jpg
  • kenwood-098.jpg
  • kenwood-099.jpg
  • kenwood-100.jpg
  • kenwood-existing-conditions.jpg
  • kenwood.jpg
  • presentation2.jpg
Click Here for Project Updates

This is a culvert replacement project on Kenwood Road near Creekwood Court.  A 96-inch corrugated metal pipe is severely rusted on both ends and is currently failing.  In 2018 the north edge section of pavement cracked resulting in the shoulder sloughing.  A temporary repair to the pipe was completed while design of a permanent replacement structure was being completed. *Indicates changes approved by Board of Commissioners


Latest Update:

Kenwood Road is now open to all traffic. The construction of a double 8-ft X 8-ft concrete box culvert is complete. Expect periodic lane closures with minor delays while final tasks are being completed over the next few weeks. 

Timeline:

  • 2/28/2018 Temporary Repair
  • 9/23/2019 All necessary ROW acquired
  • 3/13/2020 Final plans approved
  • 3/19/2020 Invitation to Bid
  • 4/08/2020 Bid Opening
  • 5/06/2020 Notice to Proceed to Contractor
  • 5/15/2020 Pre-Construction Meeting
  • 6/10/2020 Demolition and culvert forms places
  • 6/24/2020 Forming and pouring continue 
  • 7/8/2020 Pouring complete, pending backfill
  • 8/13/2020 Road open
  • 9/24/2020 Ribbon Cutting Ceremony
  • 12/09/2020 - Project pending delivery of the remainder of guardrail materials. Final grading to take place with Creekwood Court and Mercedes Trail. Milling and paving to follow. 
  • 1/27/2021 - Asphalt debris removed from curbing and catch basins
  • 2/10/2021 - Crew onsite this week for guardrail installation. Striping crew completed with project.
  • 2/24/2021 - RFI submitted by contractor for guardrail installation.
  • 4/7/2021 - Site stabilized. Pending installation of the guardrail. 
  • 5/27/2021 - Guardrail installed
  • 6/22/2021 - Project substantially complete. Pending punch list items.
  • 8/11/2021 - Contractor repaired pipe from Creekwood Court and stabilized site. Mercedes Trail punch list is complete as well.
  • 8/25/2021 - Complete. Pending vegetation.

  • Approved Budget: $229,611
  • Revised Budget: $603,699*
  • Category: Category II, Tier II
  • Expended to Date: $648,736
  • Designer: Tetra Tech
  • Contractor: Pine Valley Concrete
Copyright © 2015 Fayette County Administration. All rights reserved.