This is a culvert replacement project near 115 Brockton Court. The deteriorating 60-inch corrugated metal pipe (CMP) is being replaced with a single 5-ft by 5-ft reinforced concrete box. This project also entails utility and waterline relocations. *Budget changes reflect action by the Board of Commissioners.
Latest Update:
This project is complete.
Timeline:
- 10/14/2020 - Invitation to Bid
- 11/17/2020 - Bid Opening
- 01/14/2021 - Board Approval
- 01/19/2021 - Notice of Award
- 02/04/2021 - Notice to Proceed
- 02/19/2021 - Pre-Construction Meeting
- 07/22/2021 - All Utility Relocations complete
- 08/11/2021 - Williams Contracting Mobilization
- 10/07/2021 - Culvert construction complete
- 10/27/2021 - Roadwork complete
- 11/08/2021 - Substantial completion
- 12/08/2021 - Final Completion