170 Ridge Way Status: Design Last Updated: October 21, 2019 Anticipated Start of Construction: TBD

Budgeted & Pending
In Design
Under Construction
Completed
  • picture096.jpg
  • picture097.jpg
  • picture098.jpg
  • picture099.jpg
Click Here for Project Updates
A 42” metal pipe under Ridge Way needs to be evaluated for possible replacement. Current pipe has scoured, undercut, and corrosion failure. Pipe has joint separation.
Latest Update:

Preliminary survey work has been completed. 65% design submittal was received on 8/20/2019 and is currently in review with County Staff.

  • Approved Budget: $228,742
  • Category: Category II, Tier II
  • Expended to Date: $48,466
  • Designer: Pond