456 McBride Road Status: Completed Last Updated: July 26, 2019 Project Completed: March 04, 2016

Budgeted & Pending
In Design
Under Construction
Completed
  • 456_mcbride_road.jpg
Click Here for Project Updates
Construction involved the replacement of a failed 54" metal pipe with a 54" concrete pipe and headwalls. This project was in response to the December 2015 Flood Event that resulted in complete road and pipe failure. *Budget changes reflect action by the Board of Commissioners.
  • Approved Budget: $41,820
  • Revised Budget: $42,059*
  • Category: Category I
  • Expended to Date: $42,059
  • Designer: Fayette County Environmental Management Department
  • Contractor: McCoy Grading