120 Mercedes Trail

Click Here for Project Updates

This is a culvert replacement project on Mercedes Trail.  The deteriorating 48-inch corrugated metal pipe is being replaced with a Double 9-ft by 6-ft Reinforced Concrete Box Culvert along with minor improvements to an existing and adjacent 18-inch corrugated metal pipe. 

Latest Update:

Construction of the Mercedes Trail culvert replacement project began August 24, 2020.  Clearing is complete, downstream demolition of the existing corrugate metal pipe began August 31, 2020.  This project is on schedule to be complete this Fall. *Indicates changes approved by Board of Commissioners

Timeline: 

  • 10/5/2020 Temporary road work for traffic shift 
  • 10/6/2020 Excavation of upstream culvert area
  • 10/21/2020 Forms and steel placed to prepare for concrete. 
  • 10/30/2020 Crew completed concrete pour on upstream portion of culvert.
  • 11/6/2020 Crew removed forms. They are backfilling dirt and compacting around culvert.
  • 11/12/2020 Backfilling and compaction of the sub-base is complete. 
  • 11/20/2020 Plumbing onsite to install water main over new culvert
  • 12/18/2020 Rip rap installed
  • 12/31/20 No site activity due to wet site conditions
  • 1/13/2021 - Crew installed curbing and backfilled. Final grading, stabilization and paving pending.
  • 1/27/2021 - McLeroy Grading paved project limits. 
  • 2/10/2021 - Pine Valley crew grading areas not saturated by rain events. 
  • 2/24/2021 - Site conditions have been saturated. No activity.
  • 3/24/2021 - Crew final graded site and is ready for stabilization. 
  • 4/7/2021 - Site stabilized. Pending establishment of vegetation. 
  • 5/12/2021 - Vegetation well established.
Approved Budget: $224,070.00
Revised Budget: $471,508.00*
Category: Category II, Tier I
Expended to Date: $502,133.00
Designer: Tetra Tech
Contractor: Pine Valley Concrete

A dirt patch covered with a blue tarp, indicating a temporary or protected area  A picturesque road lined with trees and grass  A road crew is actively repairing a section of the road

A serene field with lush grass and trees in the background under a clear blue sky  A tranquil road bordered by vibrant trees and grassy areas  Cows are finalized, graded, and prepared for submission in a farm setting

Crews working on a road during the day  mercedes_existing_condition_1-3  mercedes_existing_condition_2-3

No activities scheduled this week due to wet conditions affecting safety and accessibility  Rip rap placed at the stream bank  Workers arranging and cutting materials at a job site