120 Mercedes Trail



This project was completed July 2022.
The project consisted of a culvert replacement project on Mercedes Trail.  The deteriorating 48-inch corrugated metal pipe is being replaced with a Double 9-ft by 6-ft Reinforced Concrete Box Culvert along with minor improvements to an existing and adjacent 18-inch corrugated metal pipe. 

Timeline: 

  • 10/5/2020 Temporary road work for traffic shift 
  • 10/6/2020 Excavation of upstream culvert area
  • 10/21/2020 Forms and steel placed to prepare for concrete. 
  • 10/30/2020 Crew completed concrete pour on upstream portion of culvert.
  • 11/6/2020 Crew removed forms. They are backfilling dirt and compacting around culvert.
  • 11/12/2020 Backfilling and compaction of the sub-base is complete. 
  • 11/20/2020 Plumbing onsite to install water main over new culvert
  • 12/18/2020 Rip rap installed
  • 12/31/20 No site activity due to wet site conditions
  • 1/13/2021 - Crew installed curbing and backfilled. Final grading, stabilization and paving pending.
  • 1/27/2021 - McLeroy Grading paved project limits. 
  • 2/10/2021 - Pine Valley crew grading areas not saturated by rain events. 
  • 2/24/2021 - Site conditions have been saturated. No activity.
  • 3/24/2021 - Crew final graded site and is ready for stabilization. 
  • 4/7/2021 - Site stabilized. Pending establishment of vegetation. 
  • 5/12/2021 - Vegetation well established.
Approved Budget: $224,070.00
Revised Budget: $471,508.00*
Category: Category II, Tier I
Expended to Date: $502,133.00
Designer: Tetra Tech
Contractor: Pine Valley Concrete

A dirt patch covered with a blue tarp, indicating a temporary or protected area  A picturesque road lined with trees and grass  A road crew is actively repairing a section of the road

A serene field with lush grass and trees in the background under a clear blue sky  A tranquil road bordered by vibrant trees and grassy areas  Cows are finalized, graded, and prepared for submission in a farm setting

Crews working on a road during the day  mercedes_existing_condition_1-3  mercedes_existing_condition_2-3

No activities scheduled this week due to wet conditions affecting safety and accessibility  Rip rap placed at the stream bank  Workers arranging and cutting materials at a job site