2023 SPLOST
What is SPLOST? County SPLOST Manual
City/Town Distributions
| Fayette County | $94,728,900 |
| Peachtree City | $67,380,600 |
| Fayetteville | $33,398,400 |
| Tyrone | $13,492,500 |
| Brooks | $999,600 |
| Total | $210,000,000 |

2023 SPLOST
FAYETTE COUNTY PROJECT SUMMARY
This document outlines Fayette County’s 2023 Special Purpose Local Option Sales Tax Projects. A brief description of the projects and anticipated funding requirements are outlined to address the needs of the County in many different departments. If approved, the SPLOST would be in effect for a six (6) year period from June 1, 2023, through June 30, 2029.
BUDGET SUMMARY
| Projects | Cost Estimate |
|---|---|
| Justice Center Renovation - 3rd Floor Buildout | $14,500,000 |
| Justice Center Renovation - 3rd Floor Buildout | $14,500,000 |
| Public Safety | $15,350,000 |
| Fire/EMS Training Center Buildout | $2,000,000 |
| Quint Replacement - 2 units | $3,250,000 |
| Rescue Vehicle Replacement | $1,900,000 |
| Self-Contained Breathing Apparatus Replacement | $2,000,000 |
| Ambulance Replacement - 3 | $900,000 |
| Backup 911 center and EOC at South Fayette Treatment Plant | $1,500,000 |
| Watch Office Reconfiguration with System-wide camera upgrades | $1,300,000 |
| Sheriff Tactical Driving Course & Mock Village | $2,500,000 |
| Parks, Recreation and Human Services | $16,750,000 |
| Recreational Multiuse Facility | $14,000,000 |
| Senior Services Enhancements - Transport Vehicles, Café & Meals on Wheels | $1,250,000 |
| Starr's Mill Education Facility | $1,000,000 |
| Walking Trails and Livestock Building | $500,000 |
| Stormwater Improvement Projects | $21,628,900 |
| Category I- Flooding and Safety | $3,638,000 |
| Category II - Stormwater Infrastructure Preservation | $17,990,900 |
| Transportation Improvements | $26,500,000 |
| Infrastructure Preservation and Improvements | $5,700,000 |
| Corridor Improvements/New Road Construction/Capacity Projects | $4,000,000 |
| Intersection Improvements | $11,400,000 |
| Pedestrian, Bicycle, and Multi-Use Path Projects | $4,400,000 |
| Planning Studies / Concept Reports | $1,000,000 |
| Grand Total | $94,728,900 |