130 Morning Dove Drive

Click Here for Project Updates

This is a culvert replacement project under a road that provides exclusive access to several homes in the Quail Hollow Subdivision.  Therefore, at least one lane of traffic remains open at all time. *Budget changes reflect action by the Board of Commissioners.

Latest Update:

Construction activities are complete, this project was completed in March 2020.

Timeline: 

  • 1/15/2019 ROW acquired
  • 5/06/2019 NTP issued to contractor
  • 10/14/2019 Construction began
  • 10/31/2019 Pre-cast culvert delivery
  • 11/01/2019 Utility relocations complete
  • 12/16/2019 Pre-cast retaining wall delivery
  • 1/27/2020 Culvert construction complete
  • 2/05/2020 Curb & Gutter construction complete
  • 2/26/2020 Milling of roadway complete
  • 3/09/2020 Paving complete
  • 3/23/2020  Substantial completion
Approved Budget: $244,389.00
Revised Budget: $492,389.00*
Category: Category II, Tier I
Expended to Date: $504,543.00
Designer: Tetra Tech
Contractor: Piedmont Paving, Inc.

morning-dove-drive-1  morning-dove-drive-2  morning-dove-drive-3

morning-dove-drive-4  morning-dove-drive-5  morning-dove-drive-6