Click Here for Project Updates
Construction involved the replacement of an undersized 54" metal pipe with a 60" concrete pipe and headwalls. This project was in response to the December 2015 Flood Event that resulted in shoulder and pipe failure. *Budget changes reflect action by the Board of Commissioners.
- Approved Budget: $44,523.00
- Revised Budget: $44,763.00*
- Category: Category I
- Expended to Date: $44,763.00
- Designer: Fayette County Environmental Management Department
- Contractor: McCoy Grading