Click Here for Project Updates
This project consists of the removal of the existing deteriorated 36-inch and 42-inch corrugated metal pipes (CMPs) beneath Ridge Way and extending outside of the existing right-of-way. The failing system will be replaced with 42-inch reinforced concrete pipe (RCP) under the road and 36-inch and 42-inch High Density Polyethylene pipe (HDPE) beyond the back of curb.
Latest Update:
5/14/2024: Notice to Proceed issued
6/17/2024: Construction Phase started
- Approved Budget: $228,742.00
- Revised Budget: $370,028.00*
- Category: Category II, Tier II
- Expended to Date: $398,588.00