175 Silver Leaf Drive

Click Here for Project Updates

A 48” corrugated metal pipe (CMP) under Silver Leaf Drive has been evaluated for replacement. The pipe is currently failing.

Latest Update:

This project is complete.

Timeline

  • 04/21/2021 - Invitation to Bid 
  • 05/12/2021 - Bid Opening 
  • 05/27/2021 - Board Approval 
  • 05/28/2021 - Notice of Award 
  • 06/11/2021 - Notice to Proceed 
  • 06/24/2021 - Pre-Construction Meeting 
  • 10/12/2021 - Waterline & Hydrant relocation complete
  • 10/20/2021 - Road Closed / Detour
  • 01/13/2022 - Culvert construction complete
  • 02/09/2022 - Substantial Completion
  • 04/27/2022 - Final Completion
  1. Approved Budget: $377,243.00
  2. Category: Category II, Tier I
  3. Expended to Date: $373,301.00
  4. Designer: Tetra Tech
  5. Contractor: Crawford Grading & Pipeline