211 Busbin Road



This project was completed April 2018.
An 18" concrete pipe with safety flared end sections was installed under the roadway.

  • Approved Budget: $7,575.00
  • Category: Category III
  • Expended to Date: $9,972.00
  • Designer: Fayette County Environmental Management Department
  • Contractor: Fayette County Road Department