Click Here for Project Updates
A 48” metal pipe under Cedar Trail needs to be evaluated for possible replacement. Current pipe has scoured and undercut at upstream side. Pipe is out of round, has corrosion, and no headwalls.
Latest Update:
Project is now Completed.
- 10/18/2024: Notice to Proceed Issued
- 10/24/2024: Pre-Construction Conference
- 5/5/2025: Final Completion
- Approved Budget: $58,206.00
- Revised Budget: $211,001.00*
- Category: Category II, Tier II
- Expended to Date: $161,379.00
- Designer: Pond
- Contractor: K&E Group USA, LLC