223 Cedar Trail



This project was completed May 2025.
A 48” metal pipe under Cedar Trail needs to be evaluated for possible replacement. Current pipe has scoured and undercut at upstream side. Pipe is out of round, has corrosion, and no headwalls.

  • 10/18/2024: Notice to Proceed Issued
  • 10/24/2024: Pre-Construction Conference
  • 5/5/2025: Final Completion
    • Approved Budget: $58,206.00
    • Revised Budget: $211,001.00*
    • Category: Category II, Tier II
    • Expended to Date: $161,379.00
    • Designer: Pond
    • Contractor: K&E Group USA, LLC