315 Dogwood Trail

Click Here for Project Updates

This is a culvert replacement project on a Dogwood Trail over Flat Creek.  The two existing 120-inch corrugated metal pipes have failed and show signs of possible collapse.  The proposed system is a 48-ft by 14-ft concrete bottomless arch culvert, which will be the largest culvert in the unincorporated County. *Indicates changes approved by Board of Commissioners

Latest Update:

Dogwood Trail open to all traffic July 30, 2020.

Timeline: 

  • 1/09/2019 Temporary repair with steel plates 
  • 3/04/2019 Temporary asphalt leveling for dip repair 
  • 4/14/2019 ROW acquired 
  • 5/30/2019 NTP issued to contractor 
  • 8/30/2019 Road closure / detour 
  • 9/02/2019 Construction began 
  • 9/11/2019 Gas company relocation delay 
  • 2/24/2019 Temporary modular bridge for gas main delivered to site 
  • 2/25/2019 Construction of modular bridge began
  • 2/28/2020 Construction of modular bridge complete 
  • 3/09/2020 Fabrication of temporary steel gas main began
  • 3/26/2020 Gas company contractor completed temporary relocation
  • 3/27/2020 County contractor back on site - failing pipes removed
  • 3/30/2020 Stream diversion construction
  • 4/02/2020 Culvert footer excavation
  • 4/15/2020 Culvert footer construction complete
  • 4/21/2020 Culvert footer forms removed
  • 5/04/2020 Culvert sections set in place
  • 5/05/2020 Culvert end sections/wingwalls set in place
  • 5/26/2020 Backfilling activities
  • 6/19/2020 Water main installation
  • 7/06/2020 Gas company contractor back on site
  • 7/09/2020 New water placed in service
  • 7/13/2020 Permanent gas main installation complete
  • 7/14/2020 Paving complete
  • 7/22/2020 AGL modular bridge being removed and site stablized. Pending guardrail.
  • 7/29/2020: Guardrail installation
  • 7/30/2020: Road open to all traffic
    • Approved Budget: $595,879.00
    • Revised Budget: $1,096,900.00*
    • Category: Category II, Tier I
    • Expended to Date: $1,165,424.00
    • Designer: Tetra Tech
    • Contractor: HELIX Group / AM Construction LLC

20200428-culvert-sections-arrive-bridge1dogwoodexisting-conditions1installed-culvertpicture099-3presentation12presentation2tempgasmainpresentation1