Constructed double 8' x 10' box culverts under the roadway. *Budget changes reflect action by the Board of Commissioners.
- Approved Budget: $511,848.00
- Revised Budget: $514,434.00*
- Category: Category I
- Expended to Date: $496,227.00
- Designer: Tetra Tech
- Contractor: Georgia Bridge & Concrete, LLC