Construction involved the replacement of a failed 54" metal pipe with a 54" concrete pipe and headwalls. This project was in response to the December 2015 Flood Event that resulted in complete road and pipe failure. *Budget changes reflect action by the Board of Commissioners.
- Approved Budget: $41,820.00
- Revised Budget: $42,059.00*
- Category: Category I
- Expended to Date: $42,059.00
- Designer: Fayette County Environmental Management Department
- Contractor: McCoy Grading