This project was completed May 2026.
This project was for construction of a multi-use path and tunnel under Redwine Road, immediately south of the Robinson Road intersection, and 1,500 feet of new path on the west side of Redwine Road and Robinson Road to connect with existing paths. The purpose of this project was to provide a permanent and safe route for pedestrians, bicyclists, and golf cart operators to cross Redwine Road and access the Starr’s Mill School Complex.
-
- Approved Budget: $900,000.00
- Revised Budget: $4,765,037.00*
- Category: Pedestrian, Bicycle, & Multi-Use Path Projects
- Expended to Date: $4,345,955.15
- Designer: Croy Engineering
- Contractor: Piedmont Paving