Dix-Lee-On Drive Full Depth Reclamation (FDR)

This project is complete.  Approximately 5,700-SY of roadway within The Dix-Lee'On subdivision was exhibiting failure due to the lack of rock base between the asphalt and the dirt subgrade.  Full Depth Reclamation (FDR), an in-place recycling method where all of the asphalt pavement section and a predetermined amount of underlying materials are treated to produce a stabilized base course.  The advantages of this method include improvement of pavement structure, restoration of desired profile, and elimination of cracks.

  • Approved Budget: $127,938.00
  • Category: Infrastructure Preservation and Improvements
  • Expended to Date: $88,751.00
  • Contractor: Atlanta Paving & Concrete Construction, Inc.