Updated 6/5/2026
This location has two intersections offset from each other by approximately 150 feet. The intersections generate above-average complaints about vehicle speed on Ebenezer Road and sight distance limitations. There are no sidewalks or multi-use paths in the area but there is high bike use, especially on weekends. This project’s goal is to improve safety, reduce vehicles speeds on Ebenezer Road, and optimize the intersections with bike use and future multi-use path expansion. *Budget changes reflect action by the Board of Commissioners.
This project is complete.
- Approved Budget: $1,500,000.00
- Revised Budget: $695,550.00*
- Category: Intersection Improvements
- Expended to Date: $540,514.96
- Designer: Croy Engineering