Redwine Road Multi-Use Path

Click Here for Project Updates

This is an existing, federal-aid, design-build project installing 1.5 miles of new multi-use path along Redwine Road. When complete, there will be a continuous path along Redwine Road from Birkdale Drive to Panther Path. The project will also include an at-grade crossing of Redwine Road near the Birkdale Drive and Quarters Road intersection. *Budget changes reflect action by the Board of Commissioners.

Latest Update:

This project is complete.

Timeline:

  • 04/09/2021 - Invitation to Bid (Rebid)
  • 05/27/2021 - Board Approval
  • 07/12/2021 - GDOT Construction Agreement
  • 09/30/2021 - GDOT Notice to Proceed to Award
  • 10/27/2021 - Notice to Proceed to Helix Group
  • 04/13/2022 - Utility Relocation
  • 10/27/2022 - New gas main being placed along southern corridor of project
  • 11/14/2023 - Project complete, with the exception of the traffic signal
  • 08/02/2024 - The signal is operational and has been working correctly. 
    • Approved Budget: $556,680.00
    • Revised Budget: $2,530,914.00*
    • Category: Pedestrian, Bicycle, & Multi-Use Path Projects
    • Expended to Date: $2,486,685.00
    • Designer: Heath & Lineback Engineers, Inc.
    • Contractor: Helix Group, Inc.