This is an existing, federal-aid, design-build project installing 1.5 miles of new multi-use path along Redwine Road. When complete, there will be a continuous path along Redwine Road from Birkdale Drive to Panther Path. The project will also include an at-grade crossing of Redwine Road near the Birkdale Drive and Quarters Road intersection. *Budget changes reflect action by the Board of Commissioners.
Latest Update:
This project is complete.
Timeline:
- 04/09/2021 - Invitation to Bid (Rebid)
- 05/27/2021 - Board Approval
- 07/12/2021 - GDOT Construction Agreement
- 09/30/2021 - GDOT Notice to Proceed to Award
- 10/27/2021 - Notice to Proceed to Helix Group
- 04/13/2022 - Utility Relocation
- 10/27/2022 - New gas main being placed along southern corridor of project
- 11/14/2023 - Project complete, with the exception of the traffic signal
- 08/02/2024 - The signal is operational and has been working correctly.
- Approved Budget: $556,680.00
- Revised Budget: $2,530,914.00*
- Category: Pedestrian, Bicycle, & Multi-Use Path Projects
- Expended to Date: $2,486,685.00
- Designer: Heath & Lineback Engineers, Inc.
- Contractor: Helix Group, Inc.