Redwine, Bernhard, Peachtree Parkway Intersection

Click Here for Project Updates

This is an existing 4-way stop intersection that experiences heavy delays in the morning and afternoon hours. It also has multi-use paths along Redwine Road. The intent is to improve operating conditions during AM and PM peak hours and improve the ability of pedestrians, bicyclists, and golf carts to safely cross the roads.

Latest Update:

This project is complete.

  • 05/19/2023 - Utility Relocation: Relocation efforts will continue once easements are secured
  • 08/22/2023 - Utility Relocation: Further relocations pending
  • 10/26/2023 - Construction: First phase of detour 
  • 11/27/2023 - Construction: Second phase of detour
  • 12/22/2023 - Construction: Road opened
  • 4/29/2024 - Construction: Cart path paving completed
    • Approved Budget: $1,200,000.00
    • Revised Budget: $3,810,066.00*
    • Category: Intersection Improvements
    • Expended to Date: $3,809,366.00
    • Designer: Croy Engineering