110 Mark Lane



Click Here for Project Updates

A 60” corrugated metal pipe (CMP) under Mark Lane has been evaluated for replacement. The current pipe is out of round and displays signs of corrosion, joint separation, failure under road, and damage at inlet near the roadway.

  • Approved Budget: $249,037.00
  • Revised Budget: $536,044.00 (BOC 9/25/2025)
  • Category: Category II, Tier II
  • Expended to Date: $500,122.97
  • Designer: Pond
Updated 4/9/2026