Click Here for Project Updates
The three (3) 84” corrugated metal pipes (CMP) under Shoal Creek Road have been evaluated for replacement. The current pipes are out of round and exhibit joint separation. Each pipe has physical damage and corrosion present.
Latest Update:
Survey work is complete, final plans have been approved, and the project is currently in the Right-of-Way acquisition phase.
- Approved Budget: $380,630.00
- Revised Budget: $1,008,092.00*
- Category: Category II, Tier II
- Expended to Date: $64,155.00
- Designer: Pond