130 Matthew Way

Click Here for Project Updates

A 72” corrugate metal pipe under Matthew Way has been evaluated for replacement. The current pipe is out of round and displays signs of corrosion, joint separation, and separation from both the flared end section and headwall.

Latest Update:

All survey work is complete, final design has been approved, and the project is currently in the Right-of-Way acquisition phase.

  • Approved Budget: $322,809.00
  • Revised Budget: $748,764.00*
  • Category: Category II, Tier II
  • Expended to Date: $62,398.00
  • Designer: Pond