Click Here for Project Updates
A 60” metal pipe under Grandchester Way needs to be evaluated for possible replacement. Current pipe has severe corrosion on the bottom and the inverts are rusted through.
- Approved Budget: $159,475.00
- Revised Budget: $276,193.00*
- Category: Category II, Tier II
- Expended to Date: $36,192.69
- Designer: Tetra Tech
Updated 4/9/2026