A 60” metal pipe under Grandchester Way needs to be evaluated for possible replacement. Current pipe has severe corrosion on the bottom and the inverts are rusted through.

Latest Update:

A meeting was held with the EOR on 12/18/2018 to discuss moving the project forward. The County gave the EOR direction to move forward with design to remain within the ROW limits. 60% design plans were submitted to the County on 3/27/2019 and are currently in review.

  • Approved Budget: $159,475.00
  • Revised Budget: $276,193.00*
  • Category: Category II, Tier II
  • Expended to Date: $43,012.00
  • Designer: Tetra Tech