266 Callaway Road

Click Here for Project Updates

Double 60” metal pipes under Callaway Road need to be evaluated for possible replacement.

Latest Update:

A meeting was held with the Engineer on 12/18/2018 to discuss moving the project forward with design. County staff are currently in discussion on design options.

  • Approved Budget: $533,218.00
  • Revised Budget: $963,052.00*
  • Category: Category II, Tier I
  • Expended to Date: $23,052.00
  • Designer: Tetra Tech
callaway_road_existing_2-3  callaway_road_existing_1-3 - Copy