364 Chappell Road

chappell_existing_conditions-3 - CopyClick Here for Project Updates

A 72” metal pipe under Chappell Road needs to be evaluated for possible replacement.

Latest Update:

The Engineer submitted IFC Design Plans on 11/13/2019. Plans are under review by County staff.

  • Approved Budget: $336,399.00
  • Revised Budget: $714,003.00*
  • Category: Category II, Tier I
  • Expended to Date: $54,003.00
  • Designer: Tetra Tech