215 Brandon Mill Circle - South



215_brandon_mill_existing_conditions-3Updated 5/7/2026
Click Here for Project Pictures

A 72” metal pipe on Brandon Mill Circle needs to be evaluated for possible replacement. Current pipe doesn’t have headwalls and pipe bending restricts capacity. Signs of flooding.

  • Approved Budget: $246,648.00
  • Revised Budget: $760,000.00 (BOC 6/13/2024)
  • Category: Category II, Tier I
  • Expended to Date: $41,825.64