115 Brockton Court

Click Here for Project Updates

This is a culvert replacement project near 115 Brockton Court. The deteriorating 60-inch corrugated metal pipe (CMP) is being replaced with a single 5-ft by 5-ft reinforced concrete box. This project also entails utility and waterline relocations. *Budget changes reflect action by the Board of Commissioners.

Latest Update:

This project is complete.

Timeline:

  • 10/14/2020 - Invitation to Bid
  • 11/17/2020 - Bid Opening
  • 01/14/2021 - Board Approval
  • 01/19/2021 - Notice of Award
  • 02/04/2021 - Notice to Proceed
  • 02/19/2021 - Pre-Construction Meeting
  • 07/22/2021 - All Utility Relocations complete
  • 08/11/2021 - Williams Contracting Mobilization
  • 10/07/2021 - Culvert construction complete
  • 10/27/2021 - Roadwork complete
  • 11/08/2021 - Substantial completion
  • 12/08/2021 - Final Completion
    • Approved Budget: $105,739.00
    • Revised Budget: $413,372.00*
    • Category: Category II, Tier II
    • Expended to Date: $394,414.00
    • Designer: Tetra Tech
    • Contractor: Williams Contracting Company, LLC

brockton-088  brockton-086  brockton-087

brockton-089  brockton-090  brockton-091

brockton-092  brockton-093  brockton-094

brockton-095  brockton-096  brockton-097

brockton-100  brockton_existing_conditions-3